{"id":267073,"date":"2018-06-22T00:00:00","date_gmt":"2018-06-22T07:00:00","guid":{"rendered":"https:\/\/sdnews.com\/updates-on-pipeline-replacement-project-in-midway-district\/"},"modified":"2018-06-22T00:00:00","modified_gmt":"2018-06-22T07:00:00","slug":"updates-on-pipeline-replacement-project-in-midway-district","status":"publish","type":"post","link":"https:\/\/test.sdnews.com\/es\/updates-on-pipeline-replacement-project-in-midway-district\/","title":{"rendered":"Updates on pipeline replacement project in Midway District"},"content":{"rendered":"<p>The Pacific Beach Pipeline South Replacement Project is replacing approximately 7.6 miles of water main and approximately 1.6 miles of sewer main in the\u00a0Midway\/Pacific Highway Corridor\u00a0and\u00a0Mission Bay\u00a0areas.\u00a0This\u00a0project will help the City of San Diego improve service reliability, reduce maintenance needs and lessen the risk of future water main breaks. What&#8217;s happening<br \/>\nConstruction has begun in the Midway area. This summer, crews are working to replace aging water and sewer pipelines on Midway Drive from Sports Arena Boulevard to Barnett Avenue. Work will occur at night at three different segments along Midway Drive.\u00a0This work is anticipated to last until September. Then construction will move back to the Mission Bay area.\u00a0Here are some project specifics:\u00a0<br \/>\nCurrent Construction Area 1:\u00a0Construction is currently taking place along Midway Drive from Sports Arena Boulevard to Kemper Street. Crews have begun potholing to locate utilities, afterward, they will begin installing a new 16-inch water main. There are no planned extended water outages during construction. Should the need for short service interruptions arise a separate public notice will be distributed to impacted properties.\u00a0<br \/>\nCurrent Construction Area 2:\u00a0Construction is currently taking place along Midway Drive between East Drive and Riley Street. Crews have begun potholing to locate utilities, once complete, they will begin installing a new sewer main.\u00a0<br \/>\nUpcoming Construction Area 3:\u00a0This summer, construction is anticipated to begin at the intersection of Rosecrans Boulevard and Midway Drive to install a new 16-inch water main. Work is expected to continue on Midway Drive in a southeastern direction for approximately 1,000 feet.\u00a0There are no planned extended water outages during construction. Should the need for short service interruptions arise a separate public notice will be distributed to impacted properties.\u00a0<br \/>\nBe advised that traffic control will be in place and may change.\u00a0Traffic control along the Midway Drive construction corridor will shift northbound and southbound lanes to a single lane in each direction. What to expect<br \/>\nAny work that requires water service shut-offs will occur with advanced notice to residents and stakeholders with the distribution of door hangers.\u00a0<br \/>\nAlways exercise caution near the work zone and note that:<br \/>\nSpeeds will be reduced in the construction area;<br \/>\nSafety measures will be implemented to ensure bicyclists and pedestrians will be allowed access throughout the project;<br \/>\nAccess to homes, businesses and emergency vehicles will be maintained at all times; and<br \/>\nRoad closures, detours and restricted access may be implemented during working hours.<br \/>\nYou will receive additional updates as the project\u00a0progresses. \u00a0 Hours and days of construction<br \/>\nNight work: Sunday through Thursday from 8:30 p.m. to 5 a.m.*<br \/>\n*Hours may vary based upon construction task and traffic impacts For specific questions about the Pacific Beach Pipeline South Replacement project:<br \/>\nCall 619-533-4207;<br \/>\nEmail\u00a0engineering@sandiego.gov;<br \/>\nVisit\u00a0Pacific Beach Pipeline South Replacement Project.<\/p>","protected":false},"excerpt":{"rendered":"<p>The Pacific Beach Pipeline South Replacement Project is replacing approximately 7.6 miles of water main and approximately 1.6 miles of sewer main in the\u00a0Midway\/Pacific Highway Corridor\u00a0and\u00a0Mission Bay\u00a0areas.\u00a0This\u00a0project will help the City of San Diego improve service reliability, reduce maintenance needs and lessen the risk of future water main breaks. What&#8217;s happening Construction has begun in [&hellip;]<\/p>","protected":false},"author":726,"featured_media":267074,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"_seopress_robots_primary_cat":"11561","_seopress_titles_title":"Updates on pipeline replacement project in Midway District","_seopress_titles_desc":"","_seopress_robots_index":"","jnews-multi-image_gallery":[],"jnews_single_post":[],"jnews_primary_category":[],"jnews_social_meta":[],"jnews_override_counter":[],"footnotes":""},"categories":[11551,11561],"tags":[],"class_list":["post-267073","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-news","category-peninsula-beacon"],"_links":{"self":[{"href":"https:\/\/test.sdnews.com\/es\/wp-json\/wp\/v2\/posts\/267073","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/test.sdnews.com\/es\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/test.sdnews.com\/es\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/test.sdnews.com\/es\/wp-json\/wp\/v2\/users\/726"}],"replies":[{"embeddable":true,"href":"https:\/\/test.sdnews.com\/es\/wp-json\/wp\/v2\/comments?post=267073"}],"version-history":[{"count":0,"href":"https:\/\/test.sdnews.com\/es\/wp-json\/wp\/v2\/posts\/267073\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/test.sdnews.com\/es\/wp-json\/wp\/v2\/media\/267074"}],"wp:attachment":[{"href":"https:\/\/test.sdnews.com\/es\/wp-json\/wp\/v2\/media?parent=267073"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/test.sdnews.com\/es\/wp-json\/wp\/v2\/categories?post=267073"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/test.sdnews.com\/es\/wp-json\/wp\/v2\/tags?post=267073"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}